1949
|
Dr.B.C.Roy first time conceived the idea of building an underground raiway for kolkata to solve the problems to some extent.
|
|
1969
|
The view to finding out an altrnate soluton to allivate the suffering of kolkatans , THE METRO POLITAN TRANSPORT PROJECT(RLYS) was set up.
|
|
1971
|
The MTP(rlys) has prepared a master plan of 5 rapid transit lines for the city of Kolkata, the totling rout length of 97.5km.
|
|
01.06.1972
|
The project was sanctioned by governemnt.
|
|
29.12.1972
|
The foundation stone of the project laid by
smt.Indira gandhi.
|
| 1973-74 |
The construction work was started.
|
| 24.10.1984 |
CALCUTTA METRO ,India's first and asia 's fifth
became a reality with the commissioning of partial
commuterservice covering a distance of
9.40km with 5 stations between esplanade &
bhownipur.
|
| 12.11.1984 |
An another 2.15km stretch in the north between
dum dum & belgachia commuter service followed.
|
]
| 29.04.1986 |
The commuter service was extended upto tollygung
coverd 4.24km.
|
| 26.10.1992 |
The service on north section were suspended .
|
| 13.08.1994 |
The 1.62km belgachia-shyambazar section along with
dum dum-balgachia stretch was opened.
|
| 02.10.1994 |
Another 0.71km stretch from esplanade to chandini chowk
commissioned shortly.
|
| 19.02.1995 |
The shyambazar-shovabazar-girishpark(1.93km)
chandinichowk central (0.60km) stretch were opened.
|
| 27.09.1995 |
Service on the entire stretch of metro were introduced.
|
| 1996 |
During this time more magnetic gates, escalators were added
and revolving gates were slowly phased out.
|
| March-2009 |
The construction work for line 2 was started.
|
| 22.08.2009 |
The latest extension connecting Tolly gunge(presently
Mahanayak uttamkumar) to garia bazar(presently kavi nazrul)
5.85 km metro route was inagurated.
|
| 22.09.2010 |
Railway Minister Mamata Banerjee Saturday inaugurated
the much-awaited six-kilometre expanded stretch of the
city’s Metro railway from Tollygunge to Garia bazaar in
the southern fringes.
|
| 08.10.2010 |
Mamata Banerjee flagged off the first air-conditioned (AC) train of Metro Railway in Kolkata. She also launched the Metro Services from Kavi Nazrul to Kavi Subhash Station in Kolkata and formally inaugurated the station at a function at Kavi Subhash Metro Rail Station. . |
| 1984 |
The planning for the metro started.The delhi development
authority & Urban arts comission came up with a proposal
for multi model transport. |
| 03.05.1995 |
THE DELHI METRO RAIL CORPORATION
was registred.
|
| 01.10.1998 |
The physical work started for the
project.
|
| 24.04.2002 |
The 1st line was inagurated by the hands of
atal bihari vajipayi, PM of india which is
from shahdara to rithala covered 22km
& 18 stations.
|
| 20.10.2004 |
The 2nd line of DMRC between vishwavidyalaya
& central secretariat distance of 11km &
10 stations enroute.
|
| Nov-2006 |
The 3rd line of indraprasta-barakhamba road-
dwarka for 29.9km & 28 stations enroute.
|
| 13.11.2009 |
Delhi Metro Opens Yamuna Bank - Noida Section, Enters NCR For The First Time |
| 22.12.2009 |
Delhi Metro launched a new generation of smart cards in the form of key chains for the convenience of its commuters who use these everyday.
|
| 31.12.2009 |
A specially made handcrafted model of the Metro train was launched on 31.12.2009 to celebrate the first anniversary of the Delhi Metro Museum at the Patel Chowk Metro station.
|
| 03.04.2010 |
Inauguration of 15.15 kilometer long Inderlok - Mundka Line Of Phase-II Of The Delhi Metro (The First Standard Gauge Railway Line in the Country)
|
| 21.06.2010 |
The 14.47 km long Qutub Minar - Huda City Centre (Gurgaon) Metro Corridor Opened For Public
|
| 03.09.2010 |
Central Secretariat-Qutub Minar corridor opened for commuter operations today, completing an approximately 45 km long line that connects Jahangirpuri in North Delhi to HUDA City Centre in Gurgaon.
|
|
02.10.2010 |
Metro line opened up to Sarita Vihar
|
|
01.10.2010 |
DMRC launched 'Ladies only' coach
|
| 2005 |
Construction work for phase1 of the namma metro
was scheduled to start . But it was delayed due to
change of state governement. |
| 25.04.2006 |
The indian cabinet approved the BMRCL project,
which was the budjeted at more than 5,400 crores.
|
| May-2006 |
The indian cabinet approved the BMRCL project,
which was the budjeted at more than 5,400 crores.
|
| 24.06.2006 |
The foundation stone for the phase 1 construction
was laid by P.M.Mr.Manmohan singh.
|
| 2007 |
the construction on Reach 1 of the projct between
M.G.road & baiyyappanahalli commanced.
|
| 2007-08 |
The BMRCL annonced that it would incorporate a
northen extension(yeshwanthpur-hesargatta cross)
& a part of southern extension(R.V.road-puttenahalli)
in phase 1.
|
| Oct-2008 |
The governement of karnataka approved this extension
which wold that an additional RS.1592 crores.
|
|
24.09.2010 |
Karnataka slaps notice on L&T after Metro crash on Tumkur Road |
| Dec-2011 |
The first line is scheduled to open for commuters,which would that an additional RS.1592 crores.
|
| 2012 |
The work on phase 1 was scheduled to be complete.
|
| 1974 |
The indian railways had proposed a 22km long
railway from coloba & kurla,which was shelved
due to low cost.
|
| 1999 |
The then C.M.Mr.rane & met a mumbai metro
planning group them that the RS.9,000 crore
project was consideration by the cabinet sub
committee.
|
| Jan-2004 |
The MMRDA presented the masterplan to
mumbai metro rail to the then C.M.Mr. sushilkumar shinde.
|
| Jun-2004 |
The govt. Approval was given for 13 stations devated light
rail line between ghatkopur & versova.
|
| Apr-2005 |
The delhi metro chief Mr.E.sreedharan presented phase 1
of the project to C.M. Mr.Vilasraodeshmuke who approved it.
|
| 21.06.2006 |
The foundation stone laying cermony was held by
P.M.Mr.Manmohan sing cost of 195 billions.
|
| 08.02.2008 |
The work on 11km varsova-andheri-ghatkopar corridor,
a part of phase 1 began.
|
| May-2008 |
CSR Nanjing puzen was given contract to supply 16 trains
of 4 cars each for RS 6 billions.
|
| 2010-2011 |
The phase 1 wiil be ready for commuters as project plan.
|
| 1984 |
The chennai corporation has implemented
the channai MRT project an evaluated railway system
sanctioned. |
| 16.04.2008 |
Planning commission gives in-principal approval for
the project.
|
| 21.11.2008 |
Deal signed with japan banking corporation for proceesing
59% loan at tokoyo.
|
| 20.01.2009 |
Tenders floated for phase 1 of metro project.
|
| 29.01.2009 |
Chennai metro becomes one of the fastest project to get
approved from the economic ministry, signed commoncement
by officiating F.M.Mr.pranabmukarji.
|
| 19.09.2009 |
The Hyderabad based Soma enterprise Ltd. has been
awared a INR 199.2 crores.
|
| 10.03.2009 |
A five members consortium led by Egis Rail S.A ,France
has awarded the USD 30 million general consultancy contarct
by CMRL.The other members of the consotium are
Egis india cosulting Engineers pvt.ltd. India,Maunsell consulant
Asia ltd. Hongkong,Balaji Rail Road systems India and
Yachiyo Engineering co.ltd.Japan.
|
| 20.05.2009 |
CMRCL started to evaluat the integration of metro corridor
with the planned grade separator at the junction of arcote Road
& Jawaharlal Neharu Road.
|
| 27.05.2009 |
Trail Pial Load Tests are being conducted at 3 locations in
inner ring road.
|
| 10.06.2009 |
Deputy C.M Thiru.M.K.Stalin inagurated the piling work for
construction of elevated viaduct from koyambedu to
Ashok Nagar.
|
| 23.07.2009 |
Pre-Qualification tenders invited by EMBYE consultants
for the rolling stock.
|
| 30.07.2009 |
Soiltest conducted by the DMRC at Wimco Nagar,Periyar Nagar
and Neydhal Nagar in Tiruvottiyur for chennai metro extension.
|
| 26.08.2009 |
Tenders invited for the elevated viaducts for corridor 1 from
Saidapet including station viaducts till OTA & for corridor 2
from Ashok Nagar including station viaduct till Alandur.
|
| 04.09.2009 |
Pre-Qualification tenders invited for underground & tunnels.
Invite for bids are expected around jan 2010.
|
| 31.10.2009 |
Pre-Qualification tenders invited for Trackworks(design & build)
invite for bids are expected around may 2010.
|
| 11.01.2010 |
Pre-Qualification tenders invited for Power supply system & overhead
equipements.
|
| 28.01.2010 |
L&T bags the contract for 9.73 elevated viaduct for corridor 1
from saidapet till OTA and corridor 2 from Asok Nagar till
St.thomas mount valued at INR 304.43crores.
|
| 12.02.2010 |
Tender invited for 10 elevated stations & an integrated viaduct
flyover at vadapalani.
|
| 12.03.2010 |
Tender invited forKoyambedu Depot pre-filling & 2 PQs invited for
Telecom,Platform screen doors & signalling lifts & elevators.
|
| 29.03.2010 |
Chennai metro rail project ,receives INR 2,932.6crores loan
agreement from japan .
|
| 2015 |
According to Deputy C.M.Stalin the chennai metro rail wiil be completed.
|
| Apr-2008 |
Phase 1 of the hyderabad metro rail projct was
Approved by union governement, under
Public-Private Partnership. |
| Jul-2008 |
The biddding process was completed.
The bid being awarded to consortium led by
Maytas Metro.
|
| Dec-2008 |
The satyam controvesy made Maytas to fell down.
|
| Mar-2009 |
Maytas Metro failed to achieve as per financial
closure for the project.
|
| Jul-2009 |
The Andra Pradesh govt. decided to cancel the
contract of Maytas and called for fresh bids.
|
| 16.01.2010 |
The govt. started the new bid process.
|
| 14.07.2010 |
The bid openings were held.
|
|
23.09.2010 |
SCR extends full support to metro rail
|
| Aug-2010 |
The phase 1 physical constructions will began to start.
|